  • Tier III data centre build
  • Design of site infrastructure is N+1
  • All critical plant is designed with a minimum 10% safety margin
  • 0.9 - 0.9 Power Factor on IT load, 0.95 lagging overall power factor
  • Dual incoming power feeds
  • Diesel Rotary UPS infrastructure providing a "No-breaks" electrical deployment
  • 54 hours of onsite fuel at full load
  • Cooling System N +1
  • Multiple fibre entry points
  • Multiple Meet-Me-Rooms
  • Multiple fibre and bandwidth providers available
  • 24/7 on-site engineering support